Framework Philosophy: We use Waterfall gates for governance and milestone control, combined with Agile sprint delivery within each phase for flexibility and rapid iteration. This balances the structured requirements of enterprise IT with the adaptability needed for complex technology projects.

Framework Overview

Phase 1Initiation
Phase 2Planning
Phase 3Execution
Phase 4Monitor & Control
Phase 5Closure

Phase 1: Initiation

Duration: 1–2 weeks  |  Gate: Project Charter approved by Steering Committee

Business Case

Every project must have a documented business case that articulates:

  • Problem statement: What business problem or opportunity does this project address?
  • Proposed solution: High-level description of the approach
  • Expected benefits: Quantified where possible (cost savings, efficiency gains, risk reduction)
  • Estimated cost: Capital and operational expenditure, internal resource costs
  • Timeline: High-level target dates
  • Strategic alignment: How the project supports ASI or client strategic objectives
  • Alternatives considered: Other options evaluated and why they were not selected

Template: Project Charter

📄 Project Charter

Project Name
[Descriptive project name]
Project ID
[PRJ-YYYY-NNN]
Client / Sponsor
[Client name and executive sponsor]
Project Manager
[Assigned PM name]
Project Objectives
[2-4 SMART objectives]
Scope Summary
[In scope and explicitly out of scope items]
Key Deliverables
[List of tangible deliverables]
Key Milestones
[Major milestones with target dates]
Budget
[Total approved budget: $AUD]
Key Risks
[Top 3-5 risks identified at initiation]
Key Stakeholders
[Name, role, involvement level]
Success Criteria
[How will we measure project success?]
Approval
[Steering Committee sign-off: Name, Date]

Phase 2: Planning

Duration: 1–3 weeks  |  Gate: Project Plan approved, baseline set

Work Breakdown Structure (WBS)

The PM decomposes the project scope into manageable work packages in Monday.com:

  • Level 1: Project phases
  • Level 2: Major deliverables
  • Level 3: Work packages (assigned to individuals)
  • Level 4: Tasks (granular, typically 1-5 day duration)

Resource Plan

RoleTypical AllocationSkills Required
Project Manager50-100% (based on project size)PMP/PRINCE2, stakeholder management, Monday.com
Solutions Architect25-50% during design phasesCloud architecture, enterprise networking, security
Senior Engineer(s)50-100% during executionDomain-specific (Azure, AWS, networking, security)
AI/ML Engineer25-50% for AI componentsPython, ML Ops, Azure AI, data engineering
Security Consultant25% throughoutEssential Eight, ISO 27001, penetration testing
QA/Test Engineer50% during testing phasesTest planning, automation, UAT facilitation

Template: Risk Register

📄 Risk Register

Risk IDDescriptionLikelihoodImpactScoreMitigationOwnerStatus
R-001[Risk description][H/M/L][H/M/L][1-25][Mitigation strategy][Name][Open]
R-002[Risk description][H/M/L][H/M/L][1-25][Mitigation strategy][Name][Open]

Score = Likelihood (1-5) × Impact (1-5). Scores ≥ 15 require immediate mitigation. Review weekly.

Phase 3: Execution

Duration: Variable (typically 4–16 weeks)  |  Gate: All deliverables complete and tested

Sprint Delivery Model

Within the Execution phase, work is delivered in 2-week sprints:

  • Sprint Planning: Monday morning (1 hour). PM, tech lead, and team select sprint backlog from WBS.
  • Daily Stand-up: 15 minutes, 09:15 AEST. Each team member: what I did yesterday, what I'm doing today, any blockers.
  • Sprint Review: Friday afternoon of sprint end week. Demo deliverables to client stakeholders.
  • Sprint Retrospective: Internal, Friday after sprint review. What went well, what to improve, action items.

Weekly Status Report

📄 Weekly Status Report

Project
[Project name] — [PRJ-YYYY-NNN]
Report Date
[DD/MM/YYYY]
Overall Status
[Green / Amber / Red] with brief explanation
Schedule Status
[On track / X days behind / X days ahead]
Budget Status
[On budget / $X over / $X under] — [X% of budget consumed, Y% of work complete]
Accomplishments This Week
[Bullet list of completed tasks/milestones]
Planned Next Week
[Bullet list of planned activities]
Risks & Issues
[New risks, escalated issues, decisions needed]
Client Action Items
[Items requiring client input/decision with due dates]

Phase 4: Monitoring & Control

This phase runs concurrently with Execution and continues until project closure.

KPIs Tracked

KPIMeasurementTargetReporting Frequency
Schedule Performance Index (SPI)Earned Value / Planned Value≥ 0.95Weekly
Cost Performance Index (CPI)Earned Value / Actual Cost≥ 0.95Weekly
Scope ChangesNumber of approved change requests≤ 3 per projectPer occurrence
Risk ExposureSum of (probability × impact) for open risksDecreasing trendWeekly
Defect RateDefects found per sprint / deliverableDecreasing trendPer sprint
Client SatisfactionPulse survey score at sprint reviews≥ 4/5Bi-weekly

Scope Management

All scope changes must follow this process:

  1. Change request submitted in Monday.com with business justification
  2. PM assesses impact on schedule, budget, and resources
  3. Impact assessment shared with client and Steering Committee
  4. Approval required from: client executive sponsor + ASI project board (for changes > 10% budget impact)
  5. Approved changes incorporated into project plan with updated baseline
  6. Rejected changes documented with rationale

Phase 5: Closure

Duration: 1–2 weeks  |  Gate: Client acceptance and project sign-off

Closure Activities

  1. Acceptance testing: Client UAT completed, all critical/high defects resolved
  2. Client acceptance: Formal sign-off obtained from client executive sponsor
  3. Documentation handover: All project documentation archived in Confluence (design docs, as-built diagrams, runbooks, training materials)
  4. Knowledge transfer: Handover sessions with Service Delivery/managed services team
  5. Financial closure: Final invoicing, budget reconciliation, PO closure
  6. Resource release: Team members formally released back to resource pool
  7. Lessons learned: Workshop conducted, document published
  8. Project retrospective: Internal review with project board
  9. CRM update: Project status updated in HubSpot, potential follow-on opportunities logged

Template: Lessons Learned

📄 Lessons Learned Report

Project Name & ID
[Project name] — [PRJ-YYYY-NNN]
Project Manager
[Name]
Duration
[Planned: X weeks / Actual: Y weeks]
Budget
[Planned: $X / Actual: $Y / Variance: $Z (N%)]
What Went Well
[List successes, effective practices, positive client feedback]
What Could Be Improved
[Challenges, delays, areas for improvement]
Recommendations for Future Projects
[Specific, actionable recommendations]
Client Feedback Summary
[Key points from client satisfaction survey]

Governance Structure

BodyMembersFrequencyPurpose
Steering Committee Client Exec Sponsor, ASI VP Ops, Head of PD, PM Monthly or as needed Strategic decisions, budget approval, escalation resolution, go/no-go gates
Project Board Head of PD, PM, Solutions Architect, SDM Fortnightly Resource allocation, cross-project dependencies, risk review
Project Team PM, Engineers, Consultants Daily stand-up + weekly Execution coordination, blocker resolution, sprint management

Project Management Tools

Monday.com
Primary project management tool. Used for WBS, task tracking, Gantt charts, resource allocation, sprint boards, and client-facing project dashboards.
Confluence
Documentation repository for project artefacts: design documents, meeting notes, decisions log, and as-built documentation.
Microsoft Teams
Communication hub. Each project gets a dedicated Teams channel for daily stand-ups, client communication, and file sharing.
HubSpot CRM
Tracks project commercial details, client contacts, project-to-opportunity linkage, and follow-on sales opportunities.

Project Delivery Metrics

89%
On-Time Delivery Rate
92%
On-Budget Delivery Rate
4.4/5
Client Satisfaction
$1.2M
Avg Project Value